cie logo

TARA STREET STATION REDEVELOPMENT

 

liberty-hall-View-south

Appendix B

Construction Phasing Commentary

Introduction

The proposed Works at Tara Street Station comprise an Air Rights Development above a brand new state-of-the-art concourse facility. It is a requirement that the station, which is one of the busiest in Dublin, remains operational at all times during the implementation of the development. This mandate requires careful phasing of the Works to provide a station facility that is both adequately protected from the construction activities and is operationally safe in terms of passenger flows and capacity. It is also a requirement that revenue protection is maintained throughout project implementation.

To achieve these key objectives, a construction process comprising 18 phases has been developed, and is described and illustrated in this Note, which primarily focuses on the impacts on the station. The proposed phasing utilises temporary access stairs, partial stopping up of adjacent roads, and the opening up of the arches for use as the temporary station concourse during construction. The phasing also utilises the Townsend Street entrance, and makes key assumptions regarding its use and facilities.

Within the 18 phases described, there are four different arrangements for passenger access in and out of the station and to and from the platforms. These are:

  1. Existing Situation
  2. All access from the east side of the railway arches and utilising the space beneath the arches. Public totally excluded from the west side of the railway arches. Northbound platform accessed via a temporary stair located on Poolbeg Street.
  3. New stair and escalator access to Northbound platform introduced. Narrow access route from George’s Quay introduced on the west side of the railway arches. Southbound platform accessed via temporary stair located on Luke Street.
  4. New concourse opened in full, with principal access from Tara Street and secondary access from George’s Quay. Entry and exit points to east side of the railway closed except for emergency escape. Up and down escalators, new stairs and lifts providing access to both platforms.

In broad terms, access arrangement 1 is only possible during the advance and enabling works. For all of the building works that involve basement excavation, secant pile wall construction, and construction of the building up to transfer structure level (floor 3), the public must be totally excluded from the west side of the railway arches so access arrangement 2 is required. Once the transfer structure and 3rd floor base slab are in place, works in the concourse area can commence and public access to the west side of the railway arches can start to be re-introduced. At this stage, access arrangement 3 can be deployed while the building progresses towards its uppermost floors. Station concourse fit out is not reliant on the building topping out and the top floor plant rooms being fitted out, as the station services are proposed at lower levels. Thus access arrangement 4 may be possible before the building works are completed.

BACK TO TOP

Phase A – Advance Works (Site Clearance)

Phase B – Advance Works (Temporary Concourse and Accesses)

Phase C - Existing accesses to Northbound platform no longer available. Pedestrian access to the station entirely from the east side of the railway.

Phase D (Complete Earthworks West Side)

Phase E (Basement Construction and Waterproofing)

Phase F (Structural Works to Transfer Structure)

BACK TO TOP

Phase G – New northbound platform accesses brought into use

Phase H (Transfer of Activity to East Side 1)

Phase I (Transfer of Activity to East Side 2)

Phase J (Commence East Side works)

Phase K (Southbound access removal)

Phase L (Southbound escalator removal)

BACK TO TOP

Phase M (New Southbound accesses installation)

Phase N (Instate new southbound platform accesses)

Phase O (Secondary stair access to southbound platform)

Phase P

Phase Q (Open new concourse in full)

Phase R (Works Complete)

HOME PAGE